Commissioning of Collimator Machine Protection
|
Under construction... will add here an introducition and some more details.
- EDMS note under publication with the general commissioning plan (PDF).
- Operational procedure for temperature interlock tests (PDF).
- Operational procedure for positioning interlock test (PDF), with details on how to get the analysis from logging DB.
- Status talk at the MP Panel meeting of Oct. 15th, 2008 by S. Redaelli (PDF).
- Summary status file for temperature interlock tests (XLS, PDF)
- Summary status file for positioning interlock tests (XLS, PDF)
--> Also contains the data of execution of the tests, which have to be used to retreive the results of the commissioning sequence from the logging database.
The results of the commissioning sequence for the position interlock have been systematically extracted from the logging database for all the collimators (JPG format). Browse through the results at this link (under construction).
S. Redaelli,
AB-OP -
17.10.2008