LHC Collimation Working Group |
List of pending actions from previous meetings
104th meeting of August 24th, 2009
Priority |
Task |
Responsible |
Status |
Procedure for the SPS-LSS5 change layout request for the installation of the BPM-equipped collimator prototype. | A. Bertarelli, R. Assmann | Ongoing | |
Provide energy deposition inputs for Phase II collimators to MME | Luisella Lari | Ongoing | |
RBAC and MCS deployed on all the collimators in the tunnel. | S. Redaelli, A. Masi | Ongoing | |
RBAC: roles and people for injection and dump collimators. | R. Assmann, B. Goddard, S. Redaelli | Ongoing |
103rd meeting of April 27th, 2009
Priority |
Task |
Responsible |
Status |
Inputs expected from TOTEM before the beam operation: |
TOTEM team | Pending | |
Follow-up open issues for software implementation, as found in first controls integration tests. | S. Redaelli, M.Dutour, S. Ravat | Ongoing | |
Agreement on Roman pot names for the communication between TOTEM control room and CCC during operation. |
TOTEM / OP | Done | |
Change of definition of “beam energy for physics” for the cross-calibration runs of Roman pots/collimator postioins. | MPP | Ongoing |
99th meeting of March 2nd, 2009
Priority |
Task |
Responsible |
Status |
FLUKA simulations of reference case for losses without
cryo-collimators Results presented at the collimation review. |
FLUKA team | Done | |
Comprative studies for different materials of cryo-collimator Results presented at the collimation review. |
FLUKA team | Done | |
Detailed calculation and implementation of BLM collimator thresholds | G. Bellodi, FLUKA team | Done | |
Ion requests for temperature sensor locations in IR3/IR7 Follow-up after the meeting: no additional requests for ion in the warm insertion. |
J. Jowett, G. Bellodi | Done |
98th meeting of February 16th, 2009
Priority |
Task |
Responsible |
Status |
Is it possible to compensate for the BLM cable length in order to have correct measurements for short int. time (instead than modifying the bump thresholds)? | BLM team | Pending |
97th meeting of December 17th, 2008
Priority |
Task |
Responsible |
Status |
Feasibility of bunch-by-bunch BLM gating for the LHC monitors of the transfer line collimators | BLM team | Pending | |
Review settings of collimator BLM thresholds impemented for the 2008 operation | BLM + collimation teams | Pending | |
Schottky pick-up to measure off-bucket beam properties? | F. Caspers | Pending |
96th meeting of June 16th, 2008
Priority |
Task |
Responsible |
Status |
Optimize on-line analysis required for TL collimator alignment | Coll & Inj teams | Pending | |
Follow-up SPS MD planning for collimator tests | S. Redaelli | Ongoing | |
Detailed calculation and implementation of BLM collimator thresholds | BLM team | Ongoing | |
Collimator dump thresholds for ion operation | J. Jowett | Pending |
94th meeting of February 18th, 2008
Priority |
Task |
Responsible |
Status |
Submit a request for collimator MD's at the SPS (as discussed in the meeting) See summary in the slides of S.Readelli and overall planning discussed at the APC. |
R. Assmann | Done | |
Determine case studies for fast BLM data transmission to be tested in the 2008 SPS MD's | M. Jonker | Pending | |
Upgreda old CSS collimator FESA class to the new OP system of the FESA gateways. | M. Jonker | Done | |
Provide to the BLM team the damage limits in proton losses
per second for the various collimator types. |
R. Assmann | Done |
93rd meeting of February 4th, 2008
Priority |
Task |
Responsible |
Status |
Provide AT-VAC a list of location for additional temperature measurements in IR3 and IR7. Follow-up on Collimation meeting of March 2nd, 2009: Proposal by AT-VAC: Excel file, PDF of IR3, PDF of IR7. |
Coll. team + FLUKA + VAC | Done | |
Provide to the FLUKA team the expected vacuum pressure and residual gas distribution in IR7. |
AT-VAC | Done | |
Procurement/set-up of third collimator prototype for impedance measurements. The third prototype has been procured and is available for tests. However, it must be used for an unexpected endurance test of the mechanics (discusses at the CPS meeting of 19/02/2008). The prototype readiness for impedance measurements is POSTPONED accordingly (a delay of a few weeks is expected). |
O. Aberle | Done | |
Perform additional impedance measurement of |
R. Assmann (procurement) ABP impedance team |
Ongoing | |
Definition of energy deposition studies for collimator Phase I |
ABP + FLUKA teams |
Ongoing |
92nd meeting of January 21st, 2008
Priority |
Task |
Responsible |
Status |
Implementation of energy limits for collimator gaps | A. Masi | Done | |
Configuration of collimator inputs to the BIC's Table with BIC connections: PDF (include also collimators not installed for 2008 run). |
A. Masi | Done | |
Planning for collimator HW commissionig (per sector) First planning that takes into account the constraints from HW commissioning was presented at the CPS meeting of 19/02/2008; Further updates will be announced here. |
Followed up in the CPS meeting of 19/02/2008 | Done | |
Specification document for automatic beam-based procedures (input for AB/CO development) | R. Assmann, M. Jonker | Pending | |
Calibration and interlocking issues for the fifth collimator axis (transverse tank movement) | ATB-LPE | Pending | |
Propose temperature dump levels for the various colliator types Update, Oct. 2008: Proposal given in April 2008 to E. Blanco and fully implemented into the controls of the 2008 system (~400 temperture sensors)! Values for the first year of operation: Jaw measurement: Warning: ≥ 45 ºC Interlock: ≥ 50 ºC Measurement of cooling water temperature: Warning: ≥ 30 ºC Interlock: ≥ 35 ºC |
RA+SR | Done | |
Collimator damage level during impacts of ion beams JJ: awaiting DPA Implementation in FLUKA |
J. Jowett, R. Bruce | Pending | |
Finalize the collimator MTF steps for the hardware commissioning | T. Weiler | Done |
91st meeting of December 13th, 2007
Priority |
Task |
Responsible |
Status |
Provide details of collimator FESA classes to E. Carlier Update, summer 2008: Description of the FESA interface for movable devices described in the EDMS note number 934341 by S. Redaelli). This defines the interface for setting and measurement properties, including the MCS thresholds, as well as the machine states. |
Collimator control team | Done | |
Prepare a TCDQ class with the same set/get properties at the collimator class |
TCDQ controls team | Done | |
Follow-up TCDQ protection aspects and detailed implementation | R. Assmann, R. Schmidt, B. Goddard | Ongoing |
90th meeting of December 10th, 2007
Priority |
Task |
Responsible |
Status |
Feasibility of upgrading the collimator prototype in the SPS to the final LHC hardware for beam tests in 2008. The SPS prototype cannot be upgraded for the 2008 run. The prototype will be left into the machine with the present hardware and will be kept operational for the 2008 run. |
R. Assmann | Done | |
Procurement of collimator FESA servers | R. Assmann, M. Jonker | Done | |
Final design of collimator FESA class | M. Jonker, ATB-LPE, OP | Done | |
Follow-up of pending COCOST actions (details here) | M. Jonker | Ongoing |
Updated action list for energy deposition studies (summer 2007)
Priority |
Task |
Responsible |
Status |
Energy deposition in cold magnets from direct beam losses and gas scattering | FLUKA team | To be reported | |
Passive absorber: performance with skew halo | FLUKA team, input from ABP | Done | |
Design of absorbers with movable aperture | FLUKA team | To be reported | |
Intervention scenarios, dose to personel for passive absorber repair [FLUKA inputs are ready] |
SC-RP | Ongoing | |
Performance of one-sided system | FLUKA team, input from ABP | Ongoing | |
System performance with various commissioning scenarios (larger gaps) | FLUKA team, input from ABP | Ongoing | |
Implementation of simulation errors: flatness, tilt errors, ... | C. Bracco -> FLUKA team | Ongoing | |
IR3 FLUKA model, comparison with IPHE results | FLUKA team, input from ABP | Ongoing | |
TCT damage level and corresponding BLM thresholds (1 nominal bunch) | FLUKA team | Pending | |
TCLI protection performance | Y. Kadi | Ongoing | |
Updated BLM response matrix for commissionign scenarios (Final BLM layout) | FLUKA team, input from ABP | Pending | |
Related topics: Physics development: DPA implementation | G. Smirnov, A. Ferrari | To be reported | |
Related topics: Physics development: ion scattering | G. Smirnov, A. Ferrari | To be reported |
89th meeting of July 12th, 2007
Priority |
Task |
Responsible |
Status |
Perform measurements of collimator low-frequency impedance | F. Roncarolo, B. Salvant | Ongoing | |
Material procurement and control test stand availability for impedance measurements | R. Assmann, M. Jonker | Done | |
Finalize the layout of the passive absorbers. Do we need additional protection? Do we want to ask for a change of the vacuum layout? | R. Assmann, FLUKA team | Done | |
Investigate repair scenarios for the passive absorbers and corresponding radiation doses | Coll. Design team + SC-RP | Ongoing | |
Dust production in the Tungsten material of the passive absorbers | Collimation WG | Pending | |
Passive absorbers: energy deposition and dose studies for new operational scenarios: (1) larger collimator gaps; (2) reduced collimator system | FLUKA + SC-RP team (inputs from ABP coll. team) | Pending |
88th meeting of July 4th, 2007
Priority |
Task |
Responsible |
Status |
Implementation of crystal scattering routing in tracking tools | V. Previtali | Done |
86th meeting of May 7th, 2007
Priority |
Task |
Responsible |
Status |
Scraper design: provide assumptions/inputs for design | R. Assmann, S. Redaelli | Pending |
85th meeting of April 23rd, 2007
Priority |
Task |
Responsible |
Status |
TCDQ halo load: normalization of impacting particles | L. Sarchiapone, T. Weiler | Done | |
Follow-up of 2007 SPS MD preparation | S. Redaelli | Done |
79th meeting of November 27th, 2006
Priority |
Task |
Responsible |
Status |
BLM thresholds for ions The baseline is to use the same thresholds used for protons. |
Ion collimation team | Done | |
BLM thresholds for collimator damage (TCT in particular) | Fluka team + TS team | Pending | |
Proton losses in W/m for comparison with ion loss maps | T. Weiler | Done |
74th meeting of July 17th, 2006
Priority |
Task |
Responsible |
Status |
Temperature margins using as inputs realistic proton loss distributions | ABP team -> D. Bocian | Done |
70th meeting of May 22nd, 2006
Priority |
Task |
Responsible |
Status |
Understand different loss locations for B1 and B2 | G. Robert-Demolaize | Pending | |
IR7 Fluka studies for B2 | Fluka team | Pending | |
Include active absorbers (TCLA's) in the ion loss studies | Ion team | Ongoing | |
Ion cleaning and loss maps with different TCP and TCS settings | Ion team | Pending | |
Locations of additional BLM for ions in IR3 | Ion team | Done (Note) |
69th meeting of May 8th, 2006
Priority |
Task |
Responsible |
Status |
Effect of orbit and beta-beat on the ion losses downstream of IR7 | Ion team | Ongoing | |
Impact on the BI budget of additional BLM proposed for protons and ions | BLM team | Done | |
Why off-momentum protons touch first a TCTH instead than the TCP of IR3? | Ion team | Done | |
TCDQ halo load with single-sided collimation system | L. Sarchiapone, T. Weiler | Done | |
TCDQ halo load with missing secondary collimators | L. Sarchiapone, C. Bracco | Done |
68th meeting of March 20th - LHC ion collimation studies, 2006
Priority |
Task |
Responsible |
Status |
BLM location in the dispersion suppressor of IR7 | Ion + ABP + BLM teams | Done | |
Take into account crossing and separation bumps | LHC ion team | Ongoing | |
Check the losses in the middle of the quadrupoles and not only at the magnet end | LHC ion team | Pending | |
Setup ion collimation with SixTrack? | LHC ion team + ABP team | Pending | |
Accident scenarios with ion beams | LHC ion team + FLUKA team | Pending | |
Are TCT's required at IP2 for the early ion scheme? | LHC ion team | Done | |
Updated simulations setup: (1) Increase particle diffusion speed every tracked turn instead than every 100 turns; (2) separate load contributions from different halo types (horizontal, vertical and skew); (3) Include TCLA's at IR3 and IR7 | LHC ion team | Pending | |
Improve the efficiency by reducing the length of the primary collimators? | LHC ion team | Pending |
67th meeting of March 20th - Plan for future FLUKA activities, 2006
Priority |
Task |
Responsible |
Status |
Energy deposition studies with skew halo | ABP team | Done | |
Cross-check FLUKA and IPHE simulations (model IR3 with FLUKA and IR7 with MARS) | FLUKA and IPHE teams | Pending | |
Energy deposition at IR7 at injection energy | FLUKA team | Done | |
Write-up documentation of the work carried out in the last months | FLUKA team (Mario) | Done | |
Deposited energy in BLM's and cross-talk. | FLUKA and BLM teams | Done | |
Thermo-mechanical calculations of failure scenarios at 7 TeV with 60cm long TCP's | A. Bertarelli | Done | |
Energy balance | FLUKA team | Done | |
Deposited energy for various commissioning scenarios | ABP and FLUKA teams | Ongoing | |
Direct proton losses versus deposited energy in the cold magnets of IR7 | ABP and FLUKA teams | Pending | |
FLUKA model of IR7 for beam 2 | FLUKA team | Pending | |
Phase II studies - effect of different materials for the TCS | FLUKA team | Pending | |
Halo loads on the TCDQ and downstream elements | ABP and FLUKA teams | Done | |
Halo loads on the TDI and downstream elements | ABP and FLUKA teams | Pending | |
Failure scenarios at injection | ABP and FLUKA teams | Pending | |
Energy deposition studies for SPS and TT40 tests with beam | ABP and FLUKA teams | Done | |
Crystal studies - deposited energy by channeled halo particles | ABP and FLUKA teams | Pending | |
Define BLM thresholds for damage and deformation limits of the collimators (notably, for the ones in Tungsten) | FLUKA team | Pending |
67th meeting of March 20th - Additional items, 2006
Priority |
Task |
Responsible |
Status |
Implications of final IR7 layout on the bake-out system | R. Assmann -> AT-VAC | Done | |
Difference between IR7 and IR3 (the latter requires less absorbers) | IPHE team | Pending | |
Effect of deposited energy on the performance of various IR7 equipment | Equipment owners | Done | |
Cooling required for passive absorbers | TS-MME | Done | |
Report on tolerance for Ozone production at IR7 | O. Aberle | Pending |
Old action list from 2005
Date |
Task |
Responsible |
Completed |
10.10.05 | Cross check geometry of MBW's for the IR3 simulations of deposited energy | R. Assmann -> J.B. Jeanneret and IPHE team | Done |
Follow-up of simulation of radiation doses at the MBW's of
IR7: (1) Move passive absorbers in contact with the MBW coil (2) Scaling law for radiation doses versus absorber length (3) Try different material (W layer in critical regions?) (4) "Movable" passive absorbers, like the TCLA? |
FLUKA team | Done | |
Review simulation results of Ozone production at IR7. | A. Presland | Solved after the meeting | |
Investigate the production rate versus air speed. | A. Presland | Done | |
What is the tolerable Ozone density for IR7? | O. Aberle | Done | |
Check drawings of vacuum interconnects | R. Assmann, O. Aberle + B. Dehning for BLM's | Done | |
Provide deposited energy at the BLM locations | FLUKA team | Done | |
Larger statistics on beam loss maps for failure scenarios of secondary collimators becoming a primary collimator | ABP collimation team | Done | |
Setup tracking and beam loss simulations for beam 2 | ABP/LOC section -> ABP collimation team | Done | |
Force on the coils of the MBW magnets during field ramping. Effect on the epoxy spacer. | S. Ramberger | Done | |
19.09.05 | Compare code developed at the Kurchatov institute with ANSYS for the case with no electromagnetic effects. | A.Ryazanov's team | Pending |
Convert the presented results in SKM unit system | A.Ryazanov's team | Pending | |
Setup simulation with a real collimator geometry | A.Ryazanov's team | Pending | |
Investigate the feasibility of a target beam test in 2006 to validate the simulation code by A.Ryazanov's team | J. Lettry, R. Assmann, A. Bertarelli | Done | |
27.06.05 | Follow-up/proposal for a feedback test with collimators during the 2006 tests with beam at the SPS | R. Assmann, J. Wenninger |
Pending |
Finalize the calculations of quench limit for the various LHC superconducting magnets | R. Assmann, L. Rossi |
Pending | |
Cross-check of energy deposition simulations for proton and ion studies | V. Vlachoudis, J. Jowett, R. Bruce | Ongoing | |
Cross-check crossing and separation schemes in the simulations of ion losses | H. Braun | Pending | |
Estimate the contribution of various halo load for ion simulations | H. Braun | Pending | |
Review formulae for temperature dependence of specific heat | A. Presland, Fluka team | Done | |
Energy deposition studies for asynchronous damp at 7 TeV with misfired bunches impacting on a secondary collimator | A. Presland, input from ABP team | Done | |
Check if the deposited energy in the flanges is acceptable in the case of accident case scenario at 7 TeV | A. Presland with C. Rathjen | Done | |
13.06.05 | Energy deposition studies with 60 cm long primary collimators at IR7 | Fluka team, inputs from ABP team | Done |
Accident scenario with 60 cm long primary collimators at IR7 | Fluka team + A. Bertarelli |
Done | |
Effect of TCP angle on cleaning performance and beam loss | ABP team | Pending | |
Provide maps of deposited energy at the BLMs | Fluka team | Done | |
Follow-up the feasibility of reducing the aperture at the passive absorbers of IR7 | Fluka team + C. Rathjen |
Done | |
Deposited energy in the coil of the dogleg dipoles of IR7, at the location where the coil is close to the vacuum pipe | Fluka team | Done | |
Energy balance: how much goes into the beam pipe | Fluka team | Pending | |